Vulcan Energy Resources Limited
/ Key word(s): Miscellaneous
Managing Director and CEO, Cris Moreno, commented: “Lionheart continues to build momentum, with our Team delivering construction on schedule and within budget. The start of civil construction works at the LEP now completes all major execution milestones we set for 2026 and represents another important step forward in bringing Lionheart into production. “With few new lithium projects in the Western world under construction, and Lionheart the only one of scale in Europe, we believe the project’s strategic importance continues to grow. “We will enter 2027 with a clear focus: maintain execution discipline, advance construction and deliver a critical domestic source of lithium to strengthen Europe’s battery supply chain resilience and industrial competitiveness.”
Figure 1 – Key Lionheart milestones. Commencement of LEP civil construction works highlighted in red.
Figure 2 - Image showing Lionheart’s business segments, following the lithium molecule from the upstream source to downstream final products.
Figure 3 – Overview map of Vulcan’s flagship integrated Project Lionheart with the Landau Lithium Extraction Plant shown in teal green.
<ENDS>
Daniel Tydde | Company Secretary
Jeremy McManus | Head of Investor Relations | jmcmanus@v-er.eu | +61 422 000 675 Judith Buchan | Head of Corporate Communications | jbuchan@v-er.eu | +61 411 597 326
Please contact Vulcan’s Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu
About Vulcan Energy Disclaimer Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan’s control. Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement. This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision.
Any information in this announcement that relates to: (i) Mineral Resources and Ore Resources in relation to Project Lionheart and the Future Phases projects is extracted from the "Bridging Engineering Study Results" announcement on 16 November 2023 (Bridging Engineering Study Announcement) and the "Future Phase Pipeline - Mannheim Resources Growth" announcement on 9 July 2025 (Mannheim Resources Growth Announcement); (ii) Mineral Resources and Geothermal Resources in relation to Project Ludwig is extracted from the "Positive Preliminary Feasibility Study (PFS) outlines Vulcan's second German project showcasing repeatable development growth strategy" announcement on 3 September 2026 (Project Ludwig PFS Announcement); and (iii) Exploration Results is extracted from the "Successful production test results from first new Lionheart well” announcement dated 21 January 2026, and the "Positive start to Phase One Lionheart Project field development" announcement on 19 November 2025, all of which are available to view on Vulcan's website at https://v-er.eu. Vulcan confirms that, in respect of: (i) Mineral Resources and Ore Reserves in relation to Project Lionheart and the Future Phases projects; (ii) Mineral Resources and Geothermal Resources in relation to Project Ludwig; and (iii) Exploration Results, included in this document:
Production Targets Any information in this announcement that relates to production targets for: (i) Project Lionheart is extracted from the Bridging Engineering Study Announcement; and (ii) Project Ludwig is extracted from the Project Ludwig PFS Announcement. These announcements are available to view on Vulcan's website at https://v-er.eu. Vulcan confirms that all material assumptions underpinning the production targets included in these announcements continue to apply and have not materially changed.
This announcement may contain forecast financial information, including forecast financial information derived from the Company's production targets. Any forecast financial information is based on the material assumptions set out or referred to: (i) in the case of Project Lionheart - the Independent Expert Report included as section 17 to the "Information Memorandum" announcement on 11 December 2024 and the "Financing and FID presentation" announcement on 3 December 2025; and (ii) in the case of Project Ludwig - the Project Ludwig PFS Announcement. These announcements are available to view on Vulcan's website at https://v-er.eu. Vulcan confirms that the assumptions set out in these announcements continue to apply and have not materially changed. The Company believes that it has a reasonable basis for making the forward-looking statements in this announcement (including with respect to forecast financial information).
[1]. Based on the Phase One Lionheart production Target capacity of 24kt p.a. from Bridging Engineering Study ASX announcement 16th November 2023 and Vulcan internal estimated average EV battery size and chemistry in Europe; refer to the Competent Person Statement within this announcement. Refer to the Key Risks in Appendix 3 of the Investor Presentation dated 3 December 2025 regarding the risks associated with resource exploration and development projects
16.11.2026 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group. |
| Language: | English |
| Company: | Vulcan Energy Resources Limited |
| Unit 1, Level 11, 1 Spring Street | |
| WA 6000 Perth | |
| Australia | |
| E-mail: | dtydde@v-er.eu |
| Internet: | www.v-er.eu |
| ISIN: | AU0000066086 |
| WKN: | A2PV3A |
| Listed: | Regulated Market in Frankfurt (Prime Standard); Regulated Unofficial Market in Dusseldorf, Hamburg, Munich, Stuttgart, Tradegate BSX |
| LEI Code: | 8945006OYFHQ9HE4XE54 |
| EQS News ID: | 2435458 |
| End of News | EQS News Service |
|
|
2435458 16.11.2026 CET/CEST